Project Details
(#160772)Instructions
To submit a bid:
- Download the RFQ form
- Fill out the form
- Upload it when you click the “Submit Bid” button
All bids must have an actual price good date and be itemized to be considered a valid quote. Any bids received without the requested information will be voided. All bids must be received by 4:30 p.m. on the due date.
Please be advised that all bid submissions must be submitted exclusively through the Housing Bid Board unless otherwise noted for Request for Proposals (Sealed Bids). Any bids submitted via email, mail, or other means will not be accepted or considered.
Special Instructions
Home is a 3-bedroom 2 bathroom 2000sf pier and beam home with a gambrel roof. Inspector Kevin Mings # 580-317-3244 Case Manager Jessica Kelley 8580-642-6367 All prospective contractors are required to visit the project site before submitting a bid. Change orders due to conditions that could have been identified during the site visit will not be considered or approved.
Rough Carpentry
Remove and replace all existing soffit on the home. Install new soffit and trim on entire home. Use an unprimed plywood soffit material for a natural finish, must be a minimum 7/16" if used on 24" spacing or primed/painted smart siding, homeowner to choose type of material to be installed. 1/4" plywood will not be accepted or approved. Install new trim as required for a complete and final finish.
Special Instructions
All work done must meet or exceed 2019 IRC. All applicable licenses apply. It is highly recommended contractor view job before biding. Contractor is responsible for all line locates and permits required Contractor will be responsible for cleanup and removal of all waste and repair yard back to mowing condition. Homeowner/Property Manager will select any/all colors used for the job. Contractor is responsible for all measurements, and count of materials needed.